Six types of wiring system construction technology
The Category 6 cabling system provides a high-speed bandwidth of 2.5 times higher than the Category 5 at the transmission rate, and is higher than the 300% ACR value of the Category 5 at 100 MHz. In terms of construction and installation , the six categories are much more difficult than the super five. The construction of the Category 6 cabling system must be carried out in accordance with the specifications required by international standards. Because "the more copper cable is more sensitive to the external environment. As the transmission rate increases, the correct installation or construction will have a greater impact on system performance."
Unreasonable pipeline laying, non-standard installation steps, and inadequate management systems will affect the test results (including physical and electrical performance) of Category 6 cabling, and some will become difficult to repair, even Re-lay a link to replace. The six types of wiring systems should pay attention to the following precautions during construction.
1.1 Since the outer diameter of the six types of cables is thicker than the general five types of wires, in order to avoid the winding of the cables (especially at the elbows), the filling degree of the pipe diameter must be paid attention to when laying the pipeline, generally the inner diameter is 20 mm. It is advisable to place two six-category lines for the line pipe.
1.2 Strictly observe the construction specifications of the trunking to ensure proper cable bending radius. When the other slots are turned up, down, left, and right, the slope of the curve should be gentle. Pay attention to whether the cable can be covered without damage to the cable after the cable is sag.
1.3 In the process of paying off, pay attention to the control of the pulling force. For the cable with reel packaging, the reel should be placed on the self-made pull rod, and the pay-off end should pre-pulling a part of the cable from the reel box for the pipeline. At the other end, the pre-pull line should not be too much, avoiding the entanglement of multiple lines on the field.
1.4 After the wire drawing process is finished, the redundant cables left at both ends should be arranged and protected. When the wire is wired, follow the original rotation direction. The diameter of the coil should not be too small. Use the wire card to fix the wire groove, the ceiling or the carton. , do the labeling.
1.5 When arranging, tying, and arranging cables, the redundant cables should not be too long. Do not allow the cables to be superimposed and stressed. The coils should be consolidating and the fixed ties should not be too tight.
1.6 During the whole construction period, the construction shall be organized strictly according to the construction process. Each work shall be organized according to the construction plan and the construction network plan, and the construction tasks of this work shall be completed before the start of other follow-up work.
2. Several issues to be aware of during construction